Saturday, August 13, 2011

Progress update


Frederick Street:

Units 831-839: 
The application of the 2nd coat on the wood trim, fascia/barge boards, column etc. is in progress on the carports and at the north elevation.

Units 822-828: 
The 1st coat on the wood trim boards, fascia/barge boards, columns etc. is now in progress at the east elevation. 

Units 812-818:
The application of the 1st coat on the wood trim boards, fascia/barge boards, columns etc. is now in progress at the north and east elevations.


Williams Street:

Units 3352-3358:
The application of the 1st coat on the wood trim boards, fascia/barge boards, columns in the carport etc. is now in progress at the south elevation. 

Units 3362-3368: 
The application of the 1st coat on the wood siding and metal downpipes is now in progress at the south elevation. 

Units 3372-3378:
Mildew treatment and pressure washing are now in progress at the north and east elevations. 