Wednesday, July 27, 2011

Progress update as of July 26

Frederick street:


Units 842-848   First coat has been done. Second coat is starting tomorrow.


Units 831-839   Mildew treatment and powerwashing is complete. Prep will start tomorrow


Units 812-818  Prepwork is complete. First coat will start tomorrow.



Hendecourt Street:

Units 821-827  Painters will be doing prep in the carports in the morning, then proceeding to the exterior later in the day.

Williams Street:

Units 3352-3358  Prepwork is being done on the noth and west elevations. Continuing on east and south elevations tomorrow. 